FACILITIES PROJECTS

Completed Projects (revised 7/27/2015)

  • College of Business:
    • Lobby and Stairway Improvements - Stair railing for code compliance and wood paneling in the main lobby are installed. Project budget was $58,000. Project complete September 2014.
    • Thatcher Hall, Room 347 - Project is complete.
    • Business 221 - Completed renovation to create a boardroom-type classroom. Project budget was $100,000.  Project completed September 2014.
    • Business 223 & 225Renovated existing space to create the Dean's office suite, including four offices, storage and a reception area.  Project budget was $200,000.  Project completed September 2014.
  • College of Education:
    • Library Office ADA Evaluation-Project complete.
    • Library Suite 124 Office - Renovated storage area into two offices. Project budget was $40,000.  Project completed September 2014.
    • Library 163, Endoscopy Sink - Counter and sink added to room 163.  Project budget was $30,000.  Project completed September 2014.
  • College of Fine Art & Design:
    • Mitchell Hall Railing- Mitchell Hall balcony railing was installed. Project Complete March 2014. Cost: $24,500.
    • Mitchell Hall Backstage Facility- Elliott+ has completed the feasibility study of the facility.
    • Design Tables-Purchase Order for 99 design tables was issued based upon Design Department specifications. Budget: $100,000. Project is complete.
    • Music Building, Room 135 Flooring- Project is complete.
  • College of Math & Science:
    •  Howell Hall, Labs 350 & 215- Scope of Work: Casework and Lab improvements to accommodate users. Completion date: Feb, 2014. Approximate cost: $130,000.
  • College of Liberal Arts:
    • Communications, 103A- Door Relocation. Project is complete.
    • Communications, 119 and 121 Classrooms- Replace lighting and paint walls. Project is complete.
    • Communications, Room 115 Criminal Justice Office- Select furniture for ergonomic improvements. Design information provided to the department for their use. Project is complete.
  • Construction Projects:
    •  Olympic Strength Plaza- Project is complete.
  • Capital Projects:
    • ACM- Roof to be replaced. Project is complete.
    • Ayers- Resurfacing complete.
    • Campus lighting - new light poles will be installed along University west of Admin and on Ayers north of the library. Project is complete.
  • Physical Plant:
    • Wellness – Repainting exterior W. doors that are faded due to sun exposure.
    • Administration Building – Install additional electrical panel on the north side of building to allow for more dedicated circuits.
    • Administration Building – Replace 2nd floor ceiling tiles to match existing tiles on the first floor. 
    • Administration Building – Replace carpet in President’s office common area.  
    • Administration Building – Remediate asbestos floor tile in room 101. Replace carpet with carpet tiles. 
    • Administration Building – Replace N. entrance carpet tiles.
    • Art & Design – Replace carpet in room 107 with carpet tiles. 
    • Campus – Installed 704 placard signs on all E&G buildings in coordination with EH&S.
    • Campus – Install 15 ea. new campus bollards. 
    • Campus – Seal Labyrinth pavers. 
    • Communications – Remove and reinstall door in studio to meet current use and life safety codes.
    • CTL – Clean bathroom floor tiles on both floors. 
    • Education Bldg. – Restorative floor care on all floors.
    • Education Bldg. – Reinstall aluminum entry floor mats.
    • Education Bldg. – SW Roofing installed new roof.
    • Jazz Lab – Repair and refurbish balcony EIFS. Seal and paint to prevent water intrusion. 
    • LAR – Replace carpet room 101A, 101C, 101D, 101E, 101F. Remove existing carpet and base and replace with carpet tiles.
    • LAR – Replace carpet room 102B, 102C. Remove existing carpet and base and replace with carpet tiles.
    • LAR – Replace carpet room 105B, 105E, 105F, 105G, 105H, 105I, 105J. Remove existing carpet and base and replace with carpet tiles.
    • Library – Replace carpet in elevators with VCT. 
    • MCS – Paint and replace carpet in room 115. Remove chair railing and resurface walls. Install carpet and base over VCT flooring.
    • MCS – Paint interior hallways and door frames.
    • Music – Replace sinks and countertops in men's and women's restrooms first floor. 
    • Physical Plant – Carpet replacement of conference room and hallway.
    • Physical Plant – Remodel conference room.
    • Physical Plant – Installed new AC units in Carpentry, Access Control, Motor Pool, A&E, and Electrical shops.
    • Wellness – Clean floor tiles throughout building.
    • Wellness – Repainting exterior W. doors that are faded due to sun exposure